Importing ECAD PLC Data to existing AB Project

Automation_Builder ECAD interface supports concurrent engineering by importing the ECAD data to the existing Automation_Builder PLC project.

  1. From the main menu, select Project ‣ Import ‣ ECAD (PBF).

  2. Select the PBF file which has been created during the export from the ECAD tool.

  3. Select the PLC from the list and click OK.

    A dialog window is displayed if the Automation_Builder project provides PLCs of the identical type as defined in the PBF file.

    By selecting None in the dialog window a new PLC is defined in the ECAD tool.

  4. In the Project Compare – Differences view, click 115e4ce5c187d38c0a331390004a9415_414246a037a09ed40a33139000cddd09 to merge device signals.

    The differences between the current PLC hardware configuration in Automation_Builder and the ECAD PLC data are displayed.

  5. Select the differences as desired and click Accept Single to accept the selected difference block.

  6. Close the Project Compare – Differences view to accept the changes.