Control Station and Substation Configuration¶
The CPU can work as both, control station and substation.
Control station | Client, master, controlling station: Synonyms for a higher-level station (central station, monitors other stations) |
Control direction | Data transfer direction from the control station to the substation |
Substation | Server, slave, controlled station: synonyms for a subordinate IEC 60870-5-104 telecontrol station (which is monitored) |
Monitoring direction | Data transfer direction from the substation to the controlling station |
Configure a control station in the device tree PLC -> Interfaces -> Ethernet -> Protocols:
Right-click
.Select the control station from the list and click Add object. Configure substations and further control stations in the same way. As of Automation_Builder 1.1 any combination of control stations and substations can be configured, in due consideration of a total number of 10 stations.
Double-click the new control station node to open parameter configuration. In the Link Layer tab access to the ETHERNET interface is configured.